Gachibowli–Miyapur Road near Kothaguda reimagined with a walkway, a scooter lane and a planted kerb

A proposal for HITEC City to the Financial District

Cyberabad Scoot-to-Work

Walk, scoot or auto to the bus. Ride the bus to work. A street and bus plan to move people to the IT corridor for work, built on one idea: spine, loops, tributaries and branches.

7 routes3 loops, 3 corridors, 1 feeder
73electric buses, every 5–8 min
~110stops, each with a scooter dock
₹50 / ₹100per commute to office
~₹1,600 crwhole programme, 5 years

Documents

Pitch decks and full documents

Two pitch decks tell the story: the theory, then the plan. Six documents hold the detail, drawings and assumptions behind every number on this page.

Pitch decks

Theory: Spine, Loops and Tributaries

Why the corridor jams and the traffic model behind the plan: the body analogy, KBR Park, Dubai, the Metro Node, autos on the branches.

12 slides

Open PDF

Plan: Cyberabad Scoot-to-Work

The bus network, street edge, home-to-station streets, e-scooter, Metro Bus, two fare options, costs, rollout and the ask.

26 slides

Open PDF

Documents

0. Spine, Loops and Tributaries: Traffic Model for Cities

The theory in full: layers, examples, targets for riders and auto drivers, what has to be true.

11 pages

Open PDF

1. Cyberabad Bus Loops: Final Plan

Routes, stations, fleet, phasing, bus-lane enforcement, narrow roads, the e-scooter.

13 pages

Open PDF

2. Walk and Scoot Sidewalks: Design Guide

The street edge, five rules, Tokyo and Dubai lessons, Kothaguda example.

13 pages

Open PDF

3. Home to Station: Residential Street Design Guide

Street types, speeds, the 3–5 km catchment, Mayuri Nagar example.

9 pages

Open PDF

4. Bus Operations: Costing and Fare Proposal

Operating model, cost per km, and both fare options (₹10–20 and ₹15–30) with break-even.

11 pages

Open PDF

5. Road Upgrade: Cost and Technical Specifications

Unit rates, specs to IRC codes, cost per km, phase costs.

11 pages

Open PDF

All figures are planning approximations at 2026 prices, to be confirmed by a road-width survey, a ridership survey and operator tenders.

The problem

Today the street works for no one

Gachibowli and the Financial District have no rail at all; the metro's Blue Line ends at Raidurg. Hundreds of thousands of IT workers drive or ride two-wheelers on roads built only for cars.

Gachibowli–Miyapur Road near Kothaguda today: no footpath, kerbside parking, three general lanes
Gachibowli–Miyapur Road near Kothaguda, April 2026.

No footpath

People walk in the traffic lane, between parked cars and moving autos.

The kerb is a car park

Cars, autos and two-wheelers fill the edge of the road.

No room for buses or scooters

Three general lanes each way and nothing else. A short trip to the office is not walkable and not safe on two wheels.

The theory: a traffic model for cities

Spine, loops, tributaries and branches

Chaos is not too many vehicles. It is every vehicle going in every direction. Order comes from a hierarchy: a spine, loops, tributaries and branches, each doing only its own job and meeting the next only at fixed points.

The same homes and offices connected two ways: a tangle of individual trips, and an ordered network of spine, loop, tributaries and last-mile paths

The principle: how the body moves blood

Model diagram: a metro spine with two loops around office hubs, tributaries branching off, and last-mile paths to homes

Arterial spine

The aorta carries the largest flow. In the city: the metro line.

Circulation loops

Blood keeps moving in loops. In the city: Metro Loops of median buses round each office hub.

Tributaries

Arteries branch off to each region. In the city: Metro Corridors joining a loop at a Metro Node.

Branches

Fine capillary branches reach every cell. In the city: walking, standing e-scooters and registered autos from home to the nearest Metro Node.

Two rules make it work: the big vessels never serve a cell directly, and layers meet only at fixed junctions.

KBR Park: a loop with tributaries in Hyderabad today

Map of KBR Park in Jubilee Hills: a ring of roads about 5 km round the park, with about eight main roads joining at fixed junctions and the Jubilee Hills Check Post metro station at the north-west corner
Road data from OpenStreetMap.

Road No. 2, Road No. 10, Road No. 92 and Road No. 1 ring KBR Park in a loop of about 5 km. About eight main roads join it at fixed junctions, so trips go round the park, not through it, and the metro spine touches the loop at Jubilee Hills Check Post.

The lesson is the shape. KBR still jams at peak because every vehicle shares it; Cyberabad's Metro Loops give the median lane to buses only.

Dubai: a city built along one spine

Schematic of Dubai's Red Line along Sheikh Zayed Road with 15 stations in about 26 km, the Dubai Tram loop joining at two stations, a loop round Downtown, and feeder buses
Station positions from OpenStreetMap. Schematic.

The spine

Red Line on Sheikh Zayed Road: 15 stations in about 26 km, one every 1.9 km.

A tram loop

Through Dubai Marina and JBR, joined to the metro at DMCC and Sobha Realty.

A Downtown loop

A boulevard round Burj Khalifa, with a covered walkway to the station.

Feeders and bridges

Buses from stations into neighbourhoods; footbridges so nobody crosses the road on foot.

The model in Cyberabad

Cyberabad network coloured by layer: metro Red and Blue Lines as the spine, loops L1, L2 and L3, tributaries C1, C2, C3 and the West feeder, and a 3–5 km last-mile circle around a node
LayerBodyCyberabad
SpineAortaMetro Red Line and Blue Line
LoopCirculation loopMetro Loops L1, L2, L3 round each office hub
TributaryArteryMetro Corridors C1, C2, C3 and the West feeder
NodeJunctionAbout 110 Metro Nodes, each with a scooter dock and auto stand
BranchCapillariesLast mile by walk, e-scooter or registered auto, within 3–5 km; dedicated auto parking at every node and neighbourhood

The Metro Node: the only place where layers meet

Bus platform

In the median, for the Metro Loop or Corridor; a bus every 5–8 minutes.

Metro link

Where a loop meets the spine, a short covered walk to the metro station.

Scooter dock

Beside the crossing to the platform, on the walk-and-scoot edge.

Auto parking

Dedicated spaces for registered autos, never on the walkway or scooter lane.

Target state: everyone is served, sustainably

35–55 min

Door to door

Walk, scoot or auto to a node; a bus every 5–8 minutes; one change at most.

₹1,700–2,000

A rider's month

Bus pass plus own scooter or a shared auto at about ₹25 a seat. With the metro too, a joint pass keeps it under ₹3,000.

₹1,000+

An auto driver's day

20 private rides at ₹50–100, or 14 shared runs at ₹25 a seat, from a stand at the node.

Autos serve the branches, not the arteries

  • Dedicated stands at every node, never on the walkway or scooter lane
  • Every auto registered to a zone and tracked by GPS
  • No stopping or plying along Metro Loop and Corridor roads, phased in with drivers' unions
  • The metro gets a consistent, controlled flow of people

Key benefits

  • Serves working people and auto drivers sustainably
  • Reliable, comfortable transport
  • Cleaner air: no dust pollution, no noise pollution
  • Healthier people who walk and scoot every day
  • Less chaos: smooth, controlled movement

A private auto every day (₹50–100 a trip) would cost ₹2,200–4,400 a month on its own, so the everyday last mile is walking, a scooter or a shared auto. All figures approximate.

The idea

Walk, scoot or auto to the bus. Ride the bus to work.

Four parts that only work together. The bus carries the long part of the trip; the scooter and the walkway cover the first and last kilometre; residential streets make the trip from the gate safe; and a simple fare makes changing buses painless.

01

Bus in the median

Three one-way loops and three two-way corridors, a bus every 5–8 minutes at peak.

02

Walk-and-scoot edge

A 1.5 m walkway, 2.0 m scooter lane and planted kerb on every bus road.

03

Home-to-station streets

Slow, safe residential streets within 3–5 km of every station.

04

One simple fare

₹10–20 on the bus, ₹50–100 by auto; one tap with the metro card.

The bus network

Seven routes, each checked on the map

Every route was checked on OpenStreetMap. Where there is a separate road back, buses run one way round a loop and need only one median lane. Where there is only one main road, as from Miyapur, KPHB and Chandanagar, buses run both ways on a corridor. Loops that share a road run the same way along it, like meshed gears.

Map of the seven bus routes: loops L1, L2 and L3 in the south, corridors C1, C2 and C3 to the north and west, and the West feeder
The network: loops L1, L2, L3; corridors C1, C2, C3; West feeder W.

Routes and fleet

RouteTypeServesLengthBusesPhase
L1 CoreOne-way loop, anticlockwiseHITEC City, Madhapur, Kondapur, Kothaguda10.4 km91
L2 Financial DistrictOne-way loop, clockwiseGachibowli, Raidurg, Khajaguda, Financial District13.5 km111
L3 South-eastOne-way loop, anticlockwiseManikonda, Shaikpet15.0 km82
C1 MiyapurTwo-way corridorMiyapur, Hafeezpet to the loops7.9 km112
C2 KPHBTwo-way corridorKPHB to the loops6.2 km92
C3 WestTwo-way corridorChandanagar MMTS, Lingampally, past HCU on Old Bombay Road, Gachibowli, ISB Road, Wipro Circle12.1 km122
W West feederIn traffic, signal priorityWest of the loops, in mixed traffic13.8 km133
Network~79 km73

Why loops: one lane fits an 80-ft road

Cross-section of a loop road: walkway, scooter lane, planted kerb and car lanes on each side, with a single 4 m median bus lane and platform
A loop road in 24 m (about 80 ft).

A normal median busway needs a lane each way plus a central platform, about 7.6 to 10.6 m, and buses with right-side doors.

Because each loop road only ever carries buses one way, one 4 m lane is enough and the platform always sits on the bus's left. Standard buses with left-side doors serve every platform.

The whole street, with walkways and scooter lanes on both sides, fits in 24 m. Corridors, which carry buses both ways, need about 90 ft.

About 110 stops in all, ~90 of them median stations with open platforms, shade roofs and arrival screens, each next to a scooter dock.

Risk and response

Keep cars out of the bus lane, and plan for narrow roads

Delhi's BRT was removed in 2016 partly because cars took over its lanes and enforcement was weak. Physical barriers and automatic fines from day one avoid that.

Car-trap pits at every entry

  • Pit wider than a car's track, narrower than a bus's: buses roll over, car wheels drop in
  • Only at low-speed entry points and stations, never along the lane
  • Bollards keep two-wheelers and autos out; red surface and signs before every pit
  • About ₹10–15 lakh each; ~100 pits, ₹10–15 crore. Road-safety audit before use

AI cameras, automatic fines

  • Number-plate cameras every 300–500 m, plus a forward camera on every bus (~₹50,000 each)
  • AI spots any vehicle in the lane, day and night
  • E-challan through Cyberabad Traffic Police; fines rise with each repeat
  • Tow truck called automatically for any stopped vehicle

The lane is bus-only all day; ambulances and fire engines may use it.

Where the road is narrower, cars give way first

Road widthBusScootersWalkwayCars
90 ft and overTwo-way median lanes2.0 m kerbed lane1.5–2.0 mTwo lanes each way
80–90 ftOne-way median lane on loops; two-way on corridors2.0 m kerbed lane1.5 mTwo each way on loops, one on corridors
60–80 ftKerbside bus lane in the peak direction1.5 m painted lane, Tokyo style1.5 mOne lane each way
Pinch points under 60 ftShared lane with a bus-first signalShared at 20 km/h, pictograms1.5 mOne lane, or a one-way pair

The walkway is never cut

It keeps at least 1.5 m on every stretch.

A car lane goes first

Before the bus lane or scooter lane is narrowed. Under metro pillars, the bus runs between pillars or at the kerb.

Land purchase is the last resort

Every stretch is measured in 2027 before design.

The street edge

Every bus road gets a walk-and-scoot edge

Each side: 1.5 m walkway, 2.0 m scooter lane, 0.5 m planted kerb, then two 3 m car lanes, 10 m in all. Because buses stop in the median, the kerb never has bus bays or waiting crowds, which is what makes a continuous scooter lane possible.

Plan drawing of the street edge: walkway, scooter lane, planted kerb, dock beside the crossing to a median station
The edge in plan: walkway, scooter lane, planted kerb, and a dock at each crossing.

Five rules

1

No gaps

Walkway and lane cross gates and side streets at their own level.

2

Nothing in the walkway

Poles, stalls and signboards go in the planted kerb.

3

No stopping on the edge

A coloured kerb line, as in Tokyo.

4

A dock at every crossing

Beside each crossing to a median station.

5

Fenced corners

Set-back crossings, as in Tokyo and Dubai.

What we borrow from Tokyo and Dubai

Tokyo street with a separated walkway and painted cycle lane
Tokyo: painted lanes and kerb lines on narrow streets.
Tokyo crossing with fenced corner and set-back crossing
Tokyo: fenced corners and orderly crossings.
Dubai street with shaded walkway and separated cycle and scooter track
Dubai: separated scooter tracks and shade in the heat.

Build it in three steps

StepWhatTime₹ crore per km
Quick kitPaint, planters, bollards, temporary kerbsWeekssmall; ₹30 cr for all of Phase 1
Standard edgeKerbed walkway and scooter lane, docks, lightingMonths9–12
Full rebuildPlus covered drains, duct bank, cables underground, shadeWith road works16–22

Worked example: Gachibowli–Miyapur Road near Kothaguda

TodayKothaguda road today
ReimaginedKothaguda road reimagined with walkway, scooter lane, planted kerb and median bus lane

The first mile

Home to station

Most trips start on a residential street, not a bus road. If the first 500 metres from the gate is unsafe, dark or blocked, people take the car. Every home within 3–5 km of a station, about 10–15 minutes by scooter or auto, gets one signed access route.

Diagram of a trip from a home gate along residential streets to a median bus station
The trip from the gate to the station.
Cross-sections of three residential street types: lane, colony road and collector road
Three street types and their layouts.
15

km/h on lanes

Shared, narrow streets in front of homes.

20

km/h on colony roads

Walking strips, speed tables, lighting.

30

km/h on collector roads

With a separate scooter track.

What the fix includes

  • Walking strips, speed tables at junctions, lighting every 25–30 m
  • Clearing encroachments and parked vehicles from the route
  • Signage to the nearest station and dock
  • Resident welfare associations choose the route and open side gates towards stations

Cost

Quick kit₹0.7–1.2 cr/km
Full upgrade₹3–5 cr/km
About 60 km of routes₹130–220 cr

Worked example: Mayuri Nagar Main Road

TodayMayuri Nagar Main Road today
ReimaginedMayuri Nagar Main Road reimagined with walkways, trees and calmer traffic

The reimagined image shows the walkway and street trees; the final design also adds a scooter track and a 30 km/h limit.

The standing e-scooter

A light, slow scooter for the last 3–5 km

Max X1 foldable standing e-scooter for adults
Example: Max X1 foldable e-scooter, about ₹26,000 — less than a year of two-wheeler fuel and parking.

The vehicle

Standing e-scooter, top speed 25 km/h, slowed to 10 km/h near stations by GPS; lights, bell and indicators.

Where it rides

Scooter lanes and slow residential streets, never walkways or bus-road car lanes; parked only in docks.

How people get one

Shared fleets from 2–3 licensed operators, or buy your own.

What the state must do

Notify a legal e-scooter category (standing scooters are not clearly covered today), license operators with fleet caps, riders 16 and over with helmets.

Shared fleetScootersAt ~₹26,000 each
Phase 11,500~₹4 cr
Phase 24,000~₹10 cr
Full network8,000–10,000~₹21–26 cr

Operators buy and run fleets; shared-fleet models are usually sturdier and cost more. Operators get a GHMC permit with fleet caps, a two-hour limit to clear misparked scooters, insurance per ride and anonymised trip data shared with the city. Combined bus-and-scooter monthly pass: [₹__], to be agreed.

The Metro Bus

Board like Dubai: tap in, no conductor

In Dubai, one nol card works on metro, bus and tram, with a reader by every bus door and no conductor on board. Cyberabad’s Metro Bus works the same way.

Inside a Dubai bus: a rider taps a nol card on the red reader by the door, beside a notice that a journey needs a minimum balance of AED 7.5
Dubai: tap the nol card at the reader by the door. A trip needs a minimum balance of AED 7.5.

One card, one tap

Metro card at a reader by every door. No cash, no tickets, no conductor.

₹10 a bus, ₹20 a journey

Any buses within 60 minutes; ₹40 daily cap, ₹900 monthly pass, same fare for all.

Minimum balance to board

As in Dubai, a card needs [₹20] to start a trip, so nobody rides on an empty card.

Clean, calm, watched

Electric and air-conditioned, CCTV on board, no eating or smoking, live arrival screens.

The fare

One tap, one simple fare

Same fare for every rider. Pay with the Hyderabad Metro card, a RuPay NCMC card or an app QR ticket; no cash on buses, no conductors.

₹10

Each bus you board

Tap the validator by the door. No tap-out.

₹20

Most for one journey

Any number of buses within 60 minutes.

₹40

Daily cap

The rest of the day rides free.

₹900

Monthly pass

Unlimited rides, less than running a two-wheeler.

Why per bus, not per km

Buses are an open system: people get off onto open platforms and footpaths, not through gates as in the metro. Distance fares would need everyone to tap out inside the bus every time, and missed tap-outs mean overcharges and disputes. One tap when boarding, with a ₹20 journey cap, keeps transfers cheap, which the loop-and-corridor network depends on.

Checks and fallback

Roving inspectors with handheld readers; ₹500 penalty for riding without a tap. If long single-bus rides on C1 and C3 turn out to be common, a ₹15 corridor boarding fare is the fallback, decided on six months of tap data.

Two fare options evaluated

₹10–20 a bus ride₹15–30 a bus ride
Each bus you board / most per journey₹10 / ₹20₹15 / ₹30
Daily cap / monthly pass₹40 / ₹900₹60 / ₹1,350
Average fare per journey₹13₹19.50
Break-even, paid journeys per bus a dayabout 850about 570
Commuter's bus fares a month₹440–880₹660–1,320
Riders, for the same demandbaseline15–20% fewer

₹10–20 keeps a worker’s month under ₹3,000 but needs the city to fund a slow first year; ₹15–30 pays for itself sooner but costs riders more and carries fewer of them. A middle path: open at ₹10–20 and move corridor boardings to ₹15 if six months of tap data show the deficit is not closing.

Operations

About ₹66.5 per bus-km; break-even at 850 or 570 journeys per bus a day

Electric buses run by private operators under a gross-cost contract, paid ₹59 per km. The city adds about ₹7.5 per km for the fare system, inspectors, control room and station upkeep. Driver-only buses.

Bus and battery, 12-yr financeDriversElectricityUpkeepOperator overheadCity's costs
66

of 73 buses in service each day

12,500

bus-km a day, about 190 km per bus

₹30 cr

a year to run, about ₹8.3 lakh a day

Break-even: two fare options

Chart of daily income against the ₹8.3 lakh daily operating cost: ₹15–30 meets cost at about 570 paid journeys per bus a day, ₹10–20 at about 850
Demand at ₹10–20 fares, journeys per bus a day₹10–20: a year₹15–30: journeys₹15–30: a year
Low: 600−₹8 crore480–510−₹3 to −₹4 crore
Expected: 850about break-even680–720+₹5 to +₹7 crore
Strong: 1,100+₹8 crore880–935+₹15 to +₹17 crore

66 buses in service, ₹8.3 lakh a day to run, ₹1 lakh a day from ads and station rents, 30% of journeys using two buses. ₹15–30 assumes 15–20% fewer journeys, from a typical city-bus fare elasticity of about −0.3 to −0.4. Indian city buses in mixed traffic carry roughly 650–800 passengers per bus per day.

Costs

Streets about ₹1,400 crore; whole programme about ₹1,600 crore

Built from Hyderabad-level unit rates including GST, plus 4% traffic management and 15% design, supervision and contingency. More than half the cost of a bus road is below the surface: moving pipes and poles, covered drains, a shared duct bank, and overhead cables put underground — the scope of Bengaluru's TenderSURE streets, reportedly ₹10–20 crore per km.

Part of the networkRoad length₹ crore
Loop roads L1, L2, L3: full rebuild, one-way bus lane~32 km580–800
Corridor roads C1, C2, C3: full rebuild, two-way bus lanes~21 km420–570
West feeder: walkways and painted lane~14 km40–70
Home-to-station routes: quick kit, busiest upgraded~60 km130–220
Total at 2026 rates (central ~₹1,390 cr)1,170–1,660
₹21–23 cr

per km of bus road (loop ₹21, corridor ₹23), with drains and cable ducts

₹11 / ₹19 cr

per km, standard / full walk-and-scoot edge, both sides

₹2.2 / ₹4.2 cr

per km, one-way / two-way median bus lane

₹970 cr

cheaper option keeping existing drains

Transit capital: ₹115 crore, no buses to buy

ItemQuantity₹ crore
Depots with overnight charging240
Median stations: open platform, shade roof, arrival screens~9045
Fare system: validators, handheld readers, back office, appNetwork8
Fast chargers at route ends46
Kerbside stops on the West feeder~203
Control room and live tracking13
Contingency, about 10%10
Total115

Buses come through the per-km operating contract. With 5–6% yearly price rises over a five-year build, streets come to about ₹1,500 crore; with transit capital, the programme is about ₹1,600 crore. Possible sources: state and GHMC capital budgets, PM e-Bus Sewa support for buses and charging (eligibility to confirm), depot land from TGIIC or HMDA, and station sponsorship by IT companies.

Rollout

Start with two loops, then grow

Phase 1 covers the densest office area — HITEC City, Gachibowli, Raidurg, Khajaguda and the Financial District. It opens with temporary kerbs and paint, then is built permanently. Phase 2 goes ahead only if Phase 1 proves demand.

2027

Survey and design

Road widths on every route, a ridership survey with IT employers, a market check with operators.

2027–28

Phase 1: L1 and L2

24 km, 20 buses, about 35 stations, and the walk-and-scoot edge on the same roads. ~₹470 cr streets, opening with a ₹30 cr quick kit.

2028–29

Phase 2: C1, C2, C3, L3

41 km and 40 buses, if Phase 1 carries 25,000 trips a day. Miyapur, Hafeezpet, KPHB, Chandanagar, Manikonda, Shaikpet.

2030 onwards

Phase 3: West feeder

13 buses, and a Kokapet Neopolis loop as that area grows.

Home-to-station routes open with each phase, around its stations: Kondapur, Kothaguda, Gachibowli, Raidurg and Khajaguda first.

Risks

What could go wrong, and the plan for it

RiskResponse
Cars and two-wheelers enter the bus laneCar-trap pits at entries, bollards, AI number-plate cameras on poles and buses, automatic e-challans
Road narrower than neededPre-agreed fallback: drop a car lane, then kerbside bus lane, then shared lane with bus-first signal; walkway never cut
Metro pillars in the medianBus lane between pillars where the gap allows, otherwise at the kerb
Low ridership in year onePlan for −₹8 cr; trim off-peak km, 9 m buses, ₹15 corridor fare; Phase 2 only after 25,000 trips/day
Scooters cluttering walkwaysDock-only parking, GPS slow zones, two-hour clearing rule and fleet caps in operator permits
No legal category for standing e-scootersTelangana Transport Department notifies one before any fleet launches
Fare evasion on open platformsRoving inspectors with handheld readers, ₹500 penalty
Costs higher than estimatedRange of ₹1,170–1,660 cr carried; cheaper ₹970 cr option; costs confirmed by survey and tenders
Many agencies involvedOne lead (HUMTA) with GHMC, HMDA, TGIIC, TGSRTC, HMRL and Cyberabad Traffic Police on a single programme board

The ask

Ten decisions to start in 2027

Approve the model, set the rules that make it work, and fund and organise the first phase.

Approve the model

1

The network: spine, loops and tributaries, starting with Metro Loops L1 and L2, then corridors C1, C2, C3 and loop L3, with about 110 Metro Nodes.

2

The street standard: a walk-and-scoot edge on every bus road, and a home-to-station route within 3–5 km of every node.

3

One Metro network, one card: metro, loops and corridors under one brand and map, with a joint metro and bus pass that keeps a worker’s month under ₹3,000.

4

The fare and contract: choose ₹10–20 or ₹15–30 a bus ride, and approve a per-km contract for electric, driver-only buses.

Set the rules

5

Bus-only median lanes enforced from day one, with car-trap pits, AI cameras and e-challans through Cyberabad Traffic Police.

6

Autos on the branches: zone permits, GPS tracking and dedicated parking at every node and neighbourhood, agreed with drivers’ unions.

7

A legal e-scooter category, notified by the Telangana Transport Department, with licensed shared-fleet operators and fleet caps.

Fund and organise

8

Fund Phase 1: about ₹470 crore for streets, opening with a ₹30 crore quick kit, and ₹115 crore for depots, stations and the fare system. Seek PM e-Bus Sewa support and depot land from TGIIC or HMDA.

9

One lead agency with GHMC, HMDA, TGIIC, TGSRTC, HMRL and Cyberabad Traffic Police on one programme board.

10

Start the 2027 work: a road-width survey of every route, a ridership survey with IT employers and an operator market check. Phase 2 goes ahead once Phase 1 carries 25,000 trips a day.

Whole programme about ₹1,600 crore over five years, including streets and transit capital. All figures are planning approximations.

References

Sources and inspiration

Road data for KBR Park, Dubai station positions and the bus routes are from OpenStreetMap.